RENT / EXPENSE REGISTER · 9 OCTOBER 2026

Every expense has a place.

What rent pays for, how each cost grows, and which obligations still need funding or a price.

SLA funding starts at $6. This view interprets that as $6 per GPU-hour, then increases the added service allowance with selling price. The current $2,000 per eight-GPU system/month upper allowance and linear ramp are planning inputs. Existing insurance, ordinary service and contracted SLA duties remain costs below that threshold.

One complete scope; different funding paths

The starting scenario is 16 H100 GPUs in two assemblies: each has eight GPUs and one NVLink baseboard. For H100, this assembly is the rent unit called a “rack”. A physical cabinet can contain multiple assemblies. The site budget below includes financing, staff, operations, hardware protection, certification, SLA, electricity and green funding. The expansion comparison models an incremental expansion; it does not establish the complete facility rent floor. Initial capital, deferred equipment and unpriced obligations remain visible here.

A purple 0% means a modeled zero monthly allocation. A modeled $0 can mean already funded, deferred, not activated, or not priced. Each has a different consequence. Unpriced subcomponents stay unpriced in the register and are not silently assigned zero shares. The register documents 52 lines covering all 78 entries in the prior cost records; its supplier prices and funding evidence are still incomplete.

MONTHLY CASH BUDGET

Expenses, ordered by evidence

Confidence in the basis, not a promise of accuracy. The bins run from reproducible load calculations to unresolved scope. No line is presented as a verified project invoice or executed quote. Source-based quantities, entered assumptions and policy allowances remain distinct.

Each share = that row’s monthly allocation ÷ the total assigned monthly expense budget at the same GPU-hour price. All three scenarios use the same platform, system count and sold percentage. This cash budget includes debt principal and reserves; unpriced obligations and upfront cash are excluded. Percentages total 100% before rounding.

0% · purpleLow positive · green → yellow → red · highUnpriced · gray

This is the lean-launch planning budget, not a collected invoice, supplier quote or complete-cost certification. Site costs are counted once, then allocated across installed eight-GPU equivalents. Per-assembly costs multiply by the relevant assembly count; energy follows the modeled load. A cabinet or site cost is not repeated for each assembly, and vacancy does not erase it. The full calculator also exposes financing, staff, reserve, renewable and phase controls.

FINANCING / SHARED CASH USES

Planned financing, line by line

Uses of financing · allocation still to verify

These capital scopes are documented, but no matched ledger assigns the $4.5M assumption among them. They are not additional monthly charges or amounts to add to the loan payment.

STAFF / PEOPLE & COVERAGE

Full staffing breakdown

Payroll stages are selected by recurring budget, not elapsed years. The current operating scenario commits four people; choose three for the build-stage budget, or raise the floor for existing hires. Annual salary figures exclude unentered employer costs. Salary midpoints and raises are editable.

Staffing pay & committed team settings

Readiness gates alongside the budget

StageOwner operating requirementsFunding / evidence boundary
Build · 3 peopleFacilities lead joins the founders. CTO/CFO owns security, compute operations, broker sales, sourcing, vendors, environmental monitoring and controls. CEO/COO owns plant accountability and written emergency-spend authority; facilities lead is backup and named successor.Start collecting evidence before customers: badge access with at least one year of logs, cameras at entries and the floor, encryption at rest/in transit, environmental sensors and an incident-response plan. This is the owner control plan, not completed certification.
Go live · 4 peopleCTO deputy in place before the first customer, with an on-call rota and CTO-authored runbooks. Brokers sell against the $5/GPU-hour planning case; 70% utilization is a target, not booked demand. CTO retains commercial operations.Key-person insurance on CTO, written succession, monthly independent access-log sign-off by CEO or deputy. Premium, rota adequacy and service coverage remain to verify.
Steady state · 5 peopleCompliance officer prepares evidence and the audit. Owner target: appoint 3–4 months before first audit; Type 1 then Type 2 with a planned 6–12-month evidence window, alongside HIPAA readiness.Hiring is budget-based; audit timing still follows actual scope and evidence. Audit duration/retention are not automatically prescribed by this staffing plan. Certification upkeep and setup allowances must credit any proven overlap with payroll once.
Growth · 6 peopleNetwork operations engineer joins as workload grows. CTO shifts toward CFO; deputy or network engineer takes named internal control ownership. External advisor guides; CTO retains commercial operations without a new commercial hire.Milestone raises: facilities lead toward $100k, deputy toward $90k, reviewed against government-contract and 70% utilization milestones. Budget support alone does not prove all security duties are staffed.

SOC reporting and HIPAA readiness need scoped controls and evidence, separately from salary funding. AICPA SOC guidance; HHS risk-analysis guidance.

EQUIPMENT / ACQUISITION & COVERAGE

What the equipment funding buys

Emergency fluids accumulation

SCOPE, BASIS, PAYER & TIMING

The full expense register

How the budget is reconciled

  1. Identify the required expense, committed service and cash due date.
  2. Credit existing coverage, startup funding, earmarked cash and the same cost already included in another line.
  3. Allocate shared facility and peak-capacity costs once; meter energy and assign tenant-specific additions separately.
  4. Show operating costs, scheduled debt, faster repayment, reserve contributions and upfront capital separately.
  5. Compare those uses with collected rent. Cash created by delaying required procurement is not established profit.

Insurance quotes/limits, actual utility charges, staffing coverage, startup funding, required SLA remedies and expansion C/K/W remain open. Historical whole-site allowances are retained as evidence, not added to the current budget. The next step is to replace unallocated allowances with matched cost and funding records.